Underground 69kV Cable Replacement Project

Print
Press Enter to show all options, press Tab go to next option

In keeping with the Westerville Electric Division’s commitment to delivering reliable electric services, the City is undertaking a major public power infrastructure improvement project in 2020.

The Underground 69kV Cable Replacement Project will upgrade and replace 1.2 miles of underground high-voltage power lines installed nearly 50 years ago. This new equipment will help ensure reliable power delivery for the next 50 years. 

PROJECT AT A GLANCE

  • Schedule: March - December 2020 | 7 a.m. - 7 p.m. Monday-Friday (Some Saturdays may be permitted by the City)
  • Spring/Summer: South Hempstead Road from Colony Drive to south of Gentlewind Drive
  • Summer: South Hempstead Road from Laureen Court to south of Walnut Street
  • Fall: Under Spring Road from Towers Park to Lawrence Road
  • Contractors: Danbert Electrical Corporation and Kerite Cable Services
  • $3 million investment in public power infrastructure
  • Projected 50-year useful life
69Kv_Timeline