2009 SIDEWALK REPAIR PROGRAM

 

Month 2009

City’s Activities

Homeowner’s Activities

2009

March-April 2009

City inspectors mark sidewalks needing to be repaired

 

June 2009

Notification Letters mailed to homeowners

Review inspection report

June-September 2009

City completes tree removal and sidewalk replacement

Option 1: Homeowners complete repairs 

DEADLINE: Sept 30

October-December 2009

Replacement Trees planted by City

 

2010

January-April 2010

Option 2:  City’s contractor completes sidewalk repairs  COMPLETED: April 30

Notify City of any quality concerns

DEADLINE: April 30

May 2010

Option 2 invoices mailed to property owners

 

June 2010

 

Option 2: Full; partial; or no payment DEADLINE : June 30

July 2010

Unpaid balances certified to County Auditor for assessment on Property Taxes

 